USER PROFILE:
CUTTING-EDGE POWER SYSTEM TECHNOLOGY AT THE EDGE OF THE WORLD
As a leading utility, BC Hydro continually assesses the security and reliability of their power system protection and control. Their RTDS® Simulator, a powerful NovaCor processing unit with both conventional and communications-based I/O options, has supported their efforts in upgrading protection on 500 kV lines. This case study focuses on recent work in upgrading generator and transformer protection. Recent transformer protection upgrades took place at Masset substation, where diesel generators serve a thriving community on the remote, wild, and beautiful islands of Haida Gwaii — the traditional territory of the Haida Nation.
PROJECT FOCUS:
IMPROVING THE RELAY TESTING PROCEDURE AND REDUCING COMMISSIONING TIME
Generator protection
- Stator ground fault
- Out-of-step
- Loss of excitation
- Differential
Transformer protection
- Instantaneous & time overcurrent
- Overvoltage
- Differential
Generator protection misoperation:
A diesel generator was tripping on the differential element due to severe CT saturation on transformer energization. A supervised differential blocking scheme and the relay’s High-Security-Mode (HSM) were tested on the RTDS Simulator to solve the issue.
Transformer protection misoperation:
An already energized transformer was saturating during the energization of another transformer. This is known as sympathetic inrush and the sympathetic transformer inrush resulted in the mis-operation of the differential element of a relay protecting the two transformers. Engineers reversed the polarity of one set of transformer CTs and tested the successful modification on the RTDS Simulator.
MODELLING AND VALIDATION:
GOOD ENGINEERING FOSTERS TRUSTED RESULTS
This simulation seeks to replicate results from a historical system event — failure of a high-voltage line reactor. Plots show currents on the 500 kV line, which connects a hydroelectric dam to a major substation.
OUTCOMES:
MOVING FORWARD WITH RESULTS
Having successfully applied the RTDS Simulator in their protection planning department, BC Hydro will continue testing every protection element in a controlled laboratory environment prior to generator and transformer relay deployment. During commissioning, selected COMTRADE event files are played back to the relay, and field results are sent to the protection engineer for analysis and approval.
Real-time simulation provides BC Hydro’s engineers with a fast, flexible way to understand various power system contingencies and their effect on protective relays — and a testbed for validating modified settings and configurations.
Simulation results for testing a stator-ground fault applied at 5% of the stator winding. The RTDS Simulator’s machine models can be used for the closed-loop testing of 100% stator-ground fault protection.
LEARN MORE ABOUT HIL TESTING FOR GENERATOR AND TRANSFORMER PROTECTION AT RTDS.COM/APPLICATIONS





